Guide / Wetrooms
Topciment — Step-by-Step & Tips for Bathrooms
Comprehensive guide for build-up and workflow in bathrooms from substrate preparation through sealing.
Select substrate for detailed preparations and primer:
🛑 Before commencing the project:
• Sample Board: Always create a test sample measuring at least 60×60 cm in the correct color and refined texture for client sign-off prior to starting.
• Working Temperature: Ambient and substrate temperatures must be maintained strictly between +10 °C and +25 °C.
• Drying Times & Ventilation: Ensure active air circulation and run standard air circulators so that each layer dries fully before commencing the next (never use fan heaters). The final topcoat sealer must cross-link and cure naturally.
• Thoroughly review any substrate variations and site-specific conditions with the client prior to starting work.
🧪
Primer & Reinforcement Mesh:
Always prime the substrate with a primer specifically tailored to background porosity and the chosen build-up. Ensure the surface is sound, dry, and thoroughly cleared of contaminants and grease. On porous substrates such as concrete or tile adhesive, consolidate the surface with Acricem Resin before adhering the mesh using Primacem Plus. If applying microcement strictly to the floor or when setting the drain grate in tile adhesive,
Primapox 100 Barrier is mandatory to establish an impervious moisture-blocking seal. Specific drying and curing times are listed in the individual technical guides.
1. Bathroom Wall Build-up
Coat 1: Base Coat (Microbase)
Reinforce with fiberglass mesh and trowel out the Microbase base coat uniformly using a stainless steel trowel.
Coat 2: Base Coat (Microbase)
Sand Coat 1 with 40-grit abrasives and vacuum meticulously. Trowel Coat 2 and confirm the surface is dry right through before commencing finish coats.
Coat 3: Finish Coat (Microdeck or Microfino)
Sand the base coat with 40-grit abrasives and vacuum. Trowel an opaque, solid coat of the chosen finish material with its finer aggregate texture.
Coat 4: Finish Coat (Microdeck or Microfino)
If required, apply a second thin coat using the desired texture and technique. Never touch up or back-trowel into wet material that has already begun to set.
2. Bathroom Floor Build-up
Coat 1: Base Coat (Microbase)
Fix the fiberglass mesh across the floor and embed it into the base coat. Ensure the floor mesh and initial base coats are completed prior to applying finish coats on the walls.
Coat 2: Base Coat (Microbase)
Sand the floor with 40-grit abrasives and vacuum thoroughly. Trowel Coat 2 and confirm the bed is completely dry right through before applying finish coats.
Coat 3: Finish Coat Microdeck
Sand the base coat with 40-grit abrasives and vacuum meticulously. Trowel Microdeck thinly across the floor plane. Film build is critical on floors — excessive thickness softens the matrix and reduces point-load resistance.
Coat 4: Finish Coat Microdeck
If required, apply a second thin coat of Microdeck to achieve optimal surface density, traction, and mechanical wear resistance.
3. Final Sanding & Sealing
Once the final microcement coat has dried, sand all surfaces to the desired finish texture, vacuum meticulously, and wipe clean with a microfiber cloth prior to sealing:
Apply 2 coats of Presealer. Mask the floor to catch drips, immediately back-roll any runs on vertical surfaces, and allow to dry according to technical specifications. Following this, roll apply 2 coats of two-component polyurethane sealer (TT Topsealer Dragon) in your chosen sheen to produce an impermeable moisture barrier and allow to cure fully.
4. Workflow & Estimated Day-by-Day Schedule
Day
Bathroom Application Stage
Day 1
Site setup, masking, protection, and substrate preparation.
Day 2
Prime walls and floor. Fit reinforcement mesh and apply Wall Coat 1 (Microbase) and Floor Coat 1 (Microbase).
Day 3
Sand Base Coat 1 and vacuum thoroughly. Apply Wall Coat 2 (Microbase).
Day 4
Sand wall base coats and vacuum. Apply final coat of Microdeck or Microfino to walls.
Day 5
Lightly de-nib walls. Apply final base coat of Microbase to floor, followed by the finish coat of Microdeck to floor.
Day 6
Final precision sanding of walls and floor. Vacuum and wipe clean with microfiber cloth. Apply 2 coats of TT Presealer and allow to dry.
Day 7
Apply Coat 1 of two-component polyurethane sealer TT Topsealer Dragon and allow to cure.
Day 8
De-nib lightly (400-grit), tack wipe, and apply Coat 2 of two-component polyurethane sealer TT Topsealer Dragon.
📑 Handover to Client: Always issue care and maintenance instructions to the client upon completion so the surface is cleaned and protected using approved pH-neutral detergents. The bathroom must not be commissioned or exposed to water for at least 5–7 days while the topcoat completes its cure.
🛡️ Health & Safety & Tool Maintenance:
• Personal Protection: Wear protective gloves and safety eyewear when measuring, mixing, and applying materials. Wear an approved particulate respirator during all sanding operations.
• Tool Cleaning: Clean tools thoroughly with clean water immediately after use before materials cure. For dried residues or cured topcoats, clean tools using acetone or cleaning wipes.