TT - Substrate Preparation on Tiles (ENG)

How to make wall and floor tiles completely flat before Topciment: remove silicone, sand, prime and skim over the grout lines.

tomas martinsson
Updated by tomas martinsson
Guide / Preparation

Substrate Preparation: Skimming Over Tiles & Pavers

Instructions for preparing and skim coating tiled walls and floor tiles prior to microcement application.

🛑 Before commencing the project:
• Substrate Preparation & Cleanliness: Ensure the surface is sound, dry, and thoroughly cleared of dirt and grease.
• Working Temperature: Ambient and substrate temperatures must be maintained between +10 °C and +25 °C throughout the entire preparation phase.
• Material Selection: These guidelines are based on Ardex A46 as the repair compound, though other cementitious, water-resistant repair mortars and polymer-modified tile adhesives may also be used.
• For larger floor areas with tiles, a thin coat of self-leveling screed is recommended instead.

1. Preparation and Grinding

Removal of Silicone

Cut out and remove all soft silicone seals in corners, expansion joints, and transitions. Microcement does not adhere to silicone – all flexible sealant must be thoroughly eliminated.

Concrete Grinding

Grind tiles with a concrete grinder (fitted with a diamond cup wheel) prior to starting. This keys the glazed surface to establish a strong bond and levels down proud edges or lippage between misaligned tiles.

Textured Adhesion Primer (Ardex P4)

Apply a textured adhesion promoter (e.g. Ardex P4). The primer provides a rough mechanical key for the skim coat and reduces the risk of tile contours telegraphing through the base coats.

2. Skimming and Leveling

Fill the Grout Joints

Pre-fill all grout lines completely flush. Draw the trowel diagonally across the joints to pack them solid without dislodging the wet mortar.

Scratch Coat the Surface

Once the joints have dried, sand the surface lightly and skim the entire wall or floor to make it planar. Scrape away any proud ridges with the trowel blade just before the mortar fully cures to minimize subsequent sanding.

Substrate Sanding

Sand the entire substrate flat and vacuum meticulously. Trowel cleanly from the outset, as cementitious repair mortars cure exceptionally hard and require extensive mechanical work to flatten retrospectively.

💡 Critical for the Final Outcome:
Microcement only builds 2–3 mm in total and cannot conceal underlying substrate imperfections. If joint lines or ridges can be felt by hand, the grid pattern risks ghosting through under critical glancing light after sealing. The substrate must therefore be completely flat before moving to the next stage.

3. Next Steps: Primers & Build-up