Guide for build-up, reinforcement, and workflow when applying Topciment microcement onto floor surfaces.

🛑 Before commencing the project:
• Substrate Preparation & Cleanliness: Ensure the surface is sound, dry, and thoroughly cleared of contaminants and grease.
• Working Temperature: Ambient and substrate temperatures must be maintained strictly between +10 °C and +25 °C throughout installation and curing.
• Vinyl Sheet Flooring Outside Bathrooms: We advise against installing over vinyl flooring in general living areas. Vinyl is a soft substrate, posing high risks of indentation from furniture legs and concentrated point loads.
• Floor Layer Thickness: It is critical to keep coats thin. Over-applying finish coats results in a softer matrix with compromised compressive performance.
• Finish Coat Selection: Microdeck is standard for floor applications. Microfino can be applied in small zones, but on extensive floor plans, achieving visual uniformity becomes exceptionally difficult due to technique limitations.

1. Substrate Preparation & Reinforcement

Substrate Conditions

Concrete and self-leveling screed must be ground (40-grit silicon carbide) to open porosity and primed using Acricem Resin. On ceramic and porcelain tiles, prepare according to the tiled substrate guidelines and adhere mesh using Primacem Plus.

Reinforcement Mesh Installation

58 g fiberglass mesh is the primary choice on floors. Lay mesh butt-jointed edge-to-edge with high accuracy to prevent seams telegraphing through thin microcement coats. Secure mesh using Primacem Plus or embed directly into the wet first base coat.

2. Build-up: Microcement

Base Coats 1 & 2 (Microbase)

Trowel 2 coats of Microbase (both coats pigmented). Embed the mesh into Coat 1, while Coat 2 creates the structural, smooth foundation. Sand between coats with 40-grit silicon carbide (our black discs) or a 50-grit diamond pad, and vacuum thoroughly.

Finish Coat (Microdeck)

Trowel 1–2 ultra-thin coats of Microdeck with its finer texture profile. Avoid leaving trowel ridges and work randomly across the area. Keeping Microdeck coats thin is crucial for achieving full surface hardness without elasticity.

Final Sanding

Precision final sanding: Sand smooth and planar using fine abrasives. Clear topcoats do not fill depressions; they accentuate all substrate flaws. Always work with good task lighting. Sand Microdeck using 80-grit silicon carbide by machine (or 120-grit manually). Vacuum and wipe completely clean with a dry microfiber cloth.

3. Sealing & Topcoats (Select Method)

Option 1: Topciment Maximum Wear Resistance

Traditional specification using TT Presealer followed by hard-wearing two-component PU topcoat for elevated chemical resistance.

• TT Presealer: Apply 2 coats. Mask floor edges to prevent drops and runs; immediately back-roll drips on vertical faces. Allow to dry per technical instructions.
• Topsealer Dragon: De-nib lightly with 400-grit and roll 2 coats to form an impervious barrier against moisture ingress. Allow to cure naturally without forced air fans.
Option 2: DC Titan Vapor Permeable

Rapid-drying, breathable sealer system optimal for basement slabs on ground and time-sensitive commercial programmes.

• Titan Presealer / Cream: Apply 1 coat diluted with 10–20% clean water. Cream is strongly recommended on floor areas.
• Titan Topsealer: Apply 2 coats of PU topcoat. Fast cross-linking and short recoat intervals.

4. Step-by-Step Workflow & Execution

Step
Stage & Application
Interval / Drying Time
Step 1
Prepare substrate. Fit 58 g fiberglass mesh butt-jointed edge-to-edge.
Approx. 30–60 min *
Step 2
Trowel Base Coat 1 Microbase (pigmented) and embed mesh fully.
Approx. 3–4 hours *
Step 3
Sand Base Coat 1 (40-grit silicon carbide), vacuum meticulously, and trowel Base Coat 2 Microbase.
Approx. 3–4 hours *
Step 4
Sand Base Coat 2 (40-grit silicon carbide), vacuum, and trowel Coat 1 Microdeck thinly.
Approx. 3–4 hours *
Step 5
If required: Trowel Coat 2 Microdeck ultra-thinly for opacity.
12–24 hours
Step 6
Precision final sanding (80-grit silicon carbide), vacuum, and apply selected Presealer.
Per technical guide
Step 7
De-nib lightly if needed (400-grit), tack wipe, and roll Coat 1 Topcoat.
Per technical guide
Step 8
De-nib lightly if needed (400-grit), tack wipe, and roll Coat 2 Topcoat.
Curing begins
💨 * Accelerate Drying Using Fans:
Drying intervals for primer and cementitious coats can be shortened using standard air circulators. Never use fan heaters; rapid forced evaporation weakens cement hydration and increases shrinkage cracking risks. Final topcoats must always cross-link naturally.