TT - Application on Worktops & Splashbacks (ENG)

How to build up Topciment on a worktop and splashback, from reinforcement to the finished sealer.

tomas martinsson
Updated by tomas martinsson
Guide / Worktops

Application: Worktops & Splashbacks (Topciment)

Guide for build-up and workflow when applying Topciment microcement onto worktops and splashbacks.

🛑 Before commencing the project:
• Sample Board: Always prepare a test sample of at least 60×60 cm in the correct color and with a refined texture for client sign-off prior to starting.
• Working Temperature: Ambient and substrate temperatures must be maintained strictly between +10 °C and +25 °C throughout installation and curing.
• Rigid Substrate: The worktop must be completely rigid and stable, with all substrate joints flush and level. Movement in the carcass or substrate board will cause cracking over time.
• Disassembly: Remove sinks, hobs, and tapware prior to starting to ensure proper sanding and consistent application around all edges.
• Sequence of Work: If coating both the worktop and the splashback, always begin with the splashback.

1. Substrate Preparation & Reinforcement

Cleaning

Ensure the surface is sound, dry, and thoroughly cleared of contaminants and grease. Wash and degrease the substrate meticulously so that no residual oils can migrate into the microcement.

Chamfering Edges

Chamfer the outer perimeter edges of the worktop by a few millimeters to minimize the risk of sanding through the finish. Straight, subtly eased edges are preferable to rounded profiles.

Reinforcement & Primer

Roll adhere 50 g or 58 g fiberglass mesh across the entire horizontal surface and down the vertical edges using Primacem Plus. The mesh prevents shrinkage cracking, enhances tensile adhesion, and reinforces the perimeter edges. When coating MDF, pre-prime the board with Primacem ABS.

2. Build-up: Microcement

Base Coats 1 & 2 (Microbase)

Trowel 2 coats of Microbase (both coats pigmented). Continually scrape away excess material falling over the edges. Between coats, a dry sponge can be used to blur out ridges once the surface has become tack-free. Sand away all imperfections in the base coats using 40-grit sandpaper or a 50-grit diamond pad after each coat.

Finish Coat (Microdeck or Microfino)

Vacuum and wipe the surface thoroughly with a dry microfiber cloth. Trowel 1 coat of finish material with a refined texture. If you are satisfied with the texture and coverage, 1 coat is sufficient on the worktop; otherwise, apply a second thin coat.

Final Sanding

Precision final sanding: Sand the surface smooth and planar with fine abrasives. Clear topcoats do not conceal imperfections; they accentuate all substrate defects. Always work under strong task lighting. Sand Microdeck with 80-grit (machine) or 120-grit (hand). Sand Microfino with 120-grit (machine) or 240-grit (hand). Always sand outer edges delicately by hand.

🔒 Tip for Crisp, Clean Front Edges (Final Coat Only):
Tape the front edge when troweling the top horizontal surface. Once the top face has dried, gently sand the edge by hand. Then tape the top face precisely along the front edge and trowel the front vertical edge separately to avoid marks and overlapping ridges.

3. Sealing & Topcoats

Barrier Primer (Topsealer Pro-Plus)

Vacuum thoroughly and tack wipe with a dry microfiber cloth. Roll apply 1 thin coat of Topsealer Pro-Plus using a 4 mm mohair roller. Allow to dry for at least 6–8 hours prior to topcoat sealing.

Topcoat (Topsealer Dragon)

De-nib the surface lightly with 400-grit abrasive paper and remove dust. Apply 2 coats of two-component polyurethane sealer Topsealer Dragon with an intermediate de-nibbing (400-grit) to form an impervious barrier against moisture and household chemicals. Allow to cure naturally without fans.

4. Step-by-Step Workflow & Execution

Step
Stage & Application
Interval / Drying Time
Step 1
Clean, degrease, and chamfer edges. Roll adhere mesh with Primacem Plus.
Approx. 30–60 min *
Step 2
Trowel Base Coat 1 Microbase (pigmented).
Approx. 3 hours *
Step 3
Sand Base Coat 1 (40-grit), vacuum, and trowel Base Coat 2 Microbase.
Approx. 3 hours *
Step 4
Sand Base Coat 2 (40-grit), vacuum thoroughly, and trowel Coat 1 Finish (Microdeck/Microfino).
Approx. 3 hours *
Step 5
If required: Intermediate sand and trowel Coat 2 Finish with refined texture.
12–24 hours
Step 6
Final sanding (80/120-grit) and dust wiping. Roll 1 coat Topsealer Pro-Plus.
At least 6–8 hours
Step 7
De-nib lightly (400-grit), wipe with microfiber cloth, and roll Coat 1 Topsealer Dragon.
18–36 hours
Step 8
De-nib lightly (400-grit), wipe with microfiber cloth, and roll Coat 2 Topsealer Dragon.
Curing begins
💨 * Accelerate Drying Using Fans:
Drying intervals for primer and cementitious coats can be shortened using standard air circulators. Never use fan heaters; rapid forced evaporation weakens cement hydration and increases shrinkage cracking risks. Final topcoats must always cross-link naturally.