Skip to main content

FC - Application on Worktops (ENG)

How to build up Forcrete on a worktop, from preparation to sealer.

tomas martinsson
Updated by tomas martinsson
Guide / Worktops

Application: Worktops

Practical guide for build-up and application of Forcrete microcement on worktops.

🛑 Before commencing the project:
‱ Sample Board: Always prepare a test sample of at least 60×60 cm in the correct color and texture for client approval prior to starting.
‱ Rigid Substrate: The worktop must be completely rigid and stable, with all joints flush and level. Movement in the carcass or substrate board will cause cracking over time.
‱ Substrate Inspection: Address any substrate defects with the client prior to beginning work.

1. Surface Preparation & Reinforcement

1.
Degreasing & Cleaning: Wash and degrease existing worktops thoroughly. Grease and contaminants reduce adhesion and can bleed through the cement.
2.
Repair Defects: Repair voids and damage using non-shrink repair filler. Sand and vacuum the surface entirely clean.
3.
Reinforcement: Forcrete is reinforced with 160 g mesh, spot-glued using a hot glue gun. Always butt-joint mesh runs edge-to-edge without overlapping to avoid ridges.

2. System Selection

Option 1: Standard (XT Base) Maximum Hardness

Standard specification for maximum impact resistance and surface hardness on worktops.

1. Primer: Roll apply Forprime DPM and broadcast quartz sand. Allow to cure.
2. Base Coat 1: Sweep excess sand, fit reinforcement mesh, and trowel Microbase XT. Allow to dry.
3. Base Coat 2: Sand with 50-grit diamond pad, vacuum, and apply second coat of Microbase XT. Allow to dry.
4. Microquartz (Coat 1): Sand base coat smooth and trowel Microquartz Coarse. Allow to dry.
5. Microquartz (Coat 2): Sand lightly and apply final coat of Microquartz (Coarse, Medium, or Smooth).
Option 2: Fast-Track Build-up Time Efficient

Accelerated method enabling primer and both base coats to be applied during Day 1.

1. Primer & Base Coat 1: Prime with Monogrip or Monoprime, fit mesh, and trowel Monostone XL.
2. Drying: Force dry using fans (minimum 2 hours) until fully dry.
3. Base Coat 2: Sand lightly and trowel one coat of Microbase XT. Allow to dry.
4. Microquartz (Coat 1): Sand XT layer with 50-grit diamond pad and trowel Microquartz Coarse. Allow to dry.
5. Microquartz (Coat 2): Sand lightly and apply final coat of Microquartz (Coarse, Medium, or Smooth).
🔒 Tip for Crisp, Defined Edges:
Apply material to the top horizontal surface first and allow to dry/cure until the following day. Sand the top surface, apply masking tape exactly along the top edge, and trowel the front vertical edge separately. This prevents spills and excess build-up onto the finished top surface.

3. Final Sanding & Sealing

Once the final coat of Microquartz has cured, sand the surface smooth, vacuum thoroughly, and wipe with a microfiber cloth prior to sealing.

đŸ›Ąïž Recommended Sealer System for Worktops:
For maximum resistance against staining, heat, and daily abrasion on worktops, specify either Forshield FX + Forshield Ultra, or 2 coats of Forshield Ultra.

4. Workflow & Day-by-Day Schedule

Day
Standard (Option 1)
Fast-Track (Option 2)
Day 1
Clean, degrease, and roll Forprime DPM + sand.
Prime (Monogrip/Monoprime), fit mesh, trowel Monostone XL, force dry with fans, and trowel Microbase XT.
Day 2
Sweep sand, light sand, fit mesh, and trowel Coat 1 Microbase XT.
Sand XT layer (50-grit pad) and trowel Coat 1 Microquartz Coarse.
Day 3
Sand Base Coat 1 and trowel Coat 2 Microbase XT.
Intermediate sand and trowel Final Coat Microquartz.
Day 4
Sand Base Coat 2 and trowel Coat 1 Microquartz Coarse.
Final sanding, thorough vacuuming, and sealing (2 coats).
Day 5
Intermediate sand and trowel Final Coat Microquartz.
Complete (curing).
Day 6
Final sanding, thorough vacuuming, and sealing (2 coats).
–
⏳ Curing & Usage:
‱ Light Handling: The worktop can be handled with care after 24 hours.
‱ Installation & Fixtures: Do not install hobs, sinks, or heavy appliances for at least 5 days.
‱ Covering: Do not cover the worktop with protective paper or film during the first 14 days, as the sealer needs to breathe and reach full chemical cure.
‱ Water & Cleaning: Do not expose the surface to standing water, washing-up liquid, or cleaning chemicals during the first 7 days.

How did we do?