FC - Application on Tiled Floors (ENG)

The full Forcrete workflow on tiled floors, from sanding the tiles to sealer.

tomas martinsson
Updated by tomas martinsson
Guide / Flooring

Application: Tiled Floors & Tiles

Practical guide for build-up and application of Forcrete microcement onto tiled floors and tiles.

🛑 Before the project begins:
‱ Sample Board: Always create a test sample measuring at least 60×60 cm in the exact color and texture for client approval.
‱ Substrate Inspection: Carefully check for moisture, cracks, and any structural movement in the substrate.
‱ Underfloor Heating: Turn off underfloor heating completely at least 24 hours before commencing work.
‱ Always walk through any substrate deficiencies with the client prior to starting.
💡 Tips for tiled substrates:
‱ No pre-filling required for standard joints: Two coats of Forprime HB/FL will completely build over and conceal standard grout lines.
‱ Wide joints or uneven surfaces: If tiles are unevenly laid or grout lines are exceptionally deep and wide, a thin coat of self-leveling compound is recommended prior to starting.
‱ Check for hollow tiles: Tap across the entire floor to detect hollow sounding or loose tiles. Secure or remove all debonded tiles.

1. Substrate Preparation

1.
Remove silicone joints: Cut away all silicone and elastic sealants in corners and transitions. Microcement does not adhere to silicone.
2.
Diamond grinding: Diamond grind tiles to key the glazed surface and level any lippage between edges. Vacuum the area completely clean of all dust.

2. Build-up: Tiled Floors & Tiles

Primer: Forprime DPM

Roll out Forprime DPM evenly across the entire ground surface. Allow to cure for at least 6 hours (preferably overnight).

Coat 1: Forprime HB/FL (Base Coat with Reinforcement Mesh)

Spot glue fiberglass reinforcement mesh to the floor using a hot glue gun, butt-jointed edge to edge without overlapping. Trowel out the first coat of Forprime HB/FL and broadcast quartz sand to full saturation immediately into the wet resin. Allow to cure.

Coat 2: Forprime HB/FL (Base Coat)

Sweep up and save excess sand. Diamond grind surface flat and vacuum thoroughly. Trowel out the second coat of Forprime HB/FL and broadcast quartz sand to full saturation once again. Allow to cure.

Coat 3: Microquartz Coarse

Sweep up loose sand, sand with 40-grit sandpaper/pads, and vacuum meticulously. Trowel the first coat of pigmented Microquartz Coarse. Allow to dry.

Coat 4: Final Coat Microquartz (Coarse, Medium, or Smooth)

Intermediate sand Coat 3 and vacuum. Trowel out the final coat of Microquartz in the selected finish.

3. Final Sanding & Sealing

Once the final coat of microcement has cured, sand the surface smooth using grit sizes 50–200 depending on the desired finish. Vacuum and wipe down the floor thoroughly with a microfiber mop prior to sealing.

4. Workflow & Day-by-Day Schedule

Day
Stage (Tiled Floors & Tiles)
Day 1
Check for hollow tiles, remove silicone seals, diamond grind tiles, and roll apply Forprime DPM.
Day 2
Glue mesh, trowel Coat 1 Forprime HB/FL, and broadcast quartz sand.
Day 3
Sweep sand, diamond grind, and trowel Coat 2 Forprime HB/FL with full sand broadcast.
Day 4
Sweep sand, sand (40 grit), and trowel Microquartz Coarse (Coat 1).
Day 5
Intermediate sand and trowel Final Coat Microquartz (Coarse, Medium, or Smooth).
Day 6
Final sanding, thorough vacuuming, and application of topcoat sealer.
⚡ Time-efficient option (Save 1 day):
If working on a tight schedule, the workflow can be reduced by one full day. Diamond grind and roll Forprime DPM in the morning. As soon as the primer has cured, glue the mesh and apply the first coat of Forprime HB/FL with sand broadcast during the afternoon.
⏳ Curing & Traffic:
‱ Foot Traffic: The floor may be walked on carefully in socks after 24 hours.
‱ Furnishing: Do not furnish for at least 5 days. Always use protective furniture pads.
‱ Covering & Rugs: Do not cover the floor with rugs or protective paper for at least 14 days, as the sealer needs time to fully cure and breathe.
‱ Water & Cleaning: Do not expose the surface to water or cleaning detergents during the first 7 days.