FC - Application in Bathrooms (ENG)

The full Forcrete workflow for bathroom walls and floors, from preparation to sealer.

tomas martinsson
Updated by tomas martinsson
Guide / Wetrooms

Forcrete — Step-by-Step & Tips for Bathrooms

Complete guide for build-up and workflow in bathrooms from surface preparation to sealing.

🛑 Before the project begins:
• Sample Board: Always create a test sample measuring at least 60×60 cm in the chosen color and texture for client approval prior to starting.
• Drying Times & Ventilation: Forcrete is completely waterproof and airtight, meaning trapped moisture cannot evaporate outward later. Ensure strong ventilation and use fans so that every layer is fully dry before applying the next.
• Walk through all substrate conditions and imperfections with the client prior to beginning work.
🧪 Primer:
Always prime the substrate using the designated primer tailored to the substrate and selected build-up. Ensure the primer is thoroughly dry or fully cured before starting plaster application. In wetrooms featuring wall-adjacent linear drains, Forprime DPM must be used as the primer along connecting wall bases.

1. Bathroom Wall Build-up

Coat 1: Base Coat (Monostone XL / Microbase XT)

Embed 160 g fiberglass mesh and trowel out the base coat to aggregate thickness. Smooth over with a flexible trowel to minimize subsequent sanding.

Coat 2: Base Coat (Monostone XL / Microbase XT)

Sand Coat 1 with a 50-grit diamond pad and vacuum thoroughly. Trowel Coat 2 and verify that the substrate is completely dry before proceeding with Microquartz.

Coat 3: Microquartz Coarse

Sand the base coat with a 50-grit diamond pad and vacuum. Apply a full, opaque coat of Microquartz Coarse.

Coat 4: Final Coat Microquartz (Coarse, Medium, or Smooth)

Sand lightly with a 50-grit diamond pad. Apply the final coat of Microquartz using your chosen finish and application technique.

2. Bathroom Floor Build-up

Coat 1: Forprime HB (Base Coat with Reinforcement Mesh)

Secure the reinforcement mesh to the floor and apply Forprime HB with a flat trowel. Immediately scatter quartz sand to full saturation into the wet material.

Coat 2: Forprime HB / Microbase XT

Sweep up excess sand. Grind the floor with a concrete grinder (30-grit diamond heads) to level the surface and remove any mesh blisters. Grind edges thoroughly, then apply Coat 2 of Forprime HB (+ quartz sand broadcast) or Microbase XT.

Coat 3: Microquartz Coarse

Sweep loose sand, grind flat with a 50-grit diamond pad, and vacuum thoroughly. Trowel Microquartz Coarse, masking adjoining walls against splashes.

Coat 4: Final Coat Microquartz (Coarse, Medium, or Smooth)

Sand the floor with a 50-grit diamond pad (for Coarse) or 100-grit diamond pad (for Medium/Smooth). Vacuum thoroughly and apply the final coat.

3. Final Sanding & Sealing

Once the final coat of Microquartz has cured, sand all surfaces to the desired finish, vacuum thoroughly, and wipe with a microfiber mop prior to sealing:

4. Workflow & Day-by-Day Schedule

Day
Bathroom Stage
Day 1
Mask & protect. Prime walls and floor. Embed mesh and apply Wall Coat 1.
Day 2
Sand Wall Coat 1 and vacuum. Apply Wall Coat 2. Fit mesh on floor and apply Floor Coat 1 (Forprime HB + sand).
Day 3
Sweep sand. Sand walls and apply Microquartz Coarse (Wall Coat 3). Grind Floor Coat 1 and apply Floor Coat 2 (Forprime HB + sand or Microbase XT).
Day 4
Sand Wall Coat 3 and apply Final Wall Coat Microquartz. Grind Floor Coat 2 and apply Microquartz Coarse (Floor Coat 3).
Day 5
Sand final coarse coat on walls and apply Final Floor Coat Microquartz.
Day 6
Final sanding of walls and floor. Vacuum and microfiber mop meticulously. Apply protective topcoat.
📑 Handover to end client: Always provide care and maintenance instructions to the client upon project completion to ensure the surface is maintained with recommended pH-neutral cleaning agents.

How did we do?