FC - Application on Vinyl (ENG)

How to prepare vinyl flooring in wet rooms for Forcrete: check that the vinyl is well bonded, fill level differences and prime.

tomas martinsson
Updated by tomas martinsson
Guide / Preparation & Substrates

Application: Vinyl Flooring

Practical guide for preparation, leveling height transitions, and priming on vinyl sheet flooring in wetrooms.

🛑 Before starting the project:
‱ No blisters or debonding: Inspect the entire vinyl membrane thoroughly. The vinyl must be fully bonded with no lifting in corners or along wall upstands.
‱ Critical at floor drain: Ensure the vinyl has not debonded or flexing around the floor drain. Any trapped air or deflection beneath the vinyl will cause the microcement to crack over time.
💡 Tips for corners and finish on vinyl flooring:
‱ Vinyl floorings often feature welded overlaps and rounded corners, which can make achieving sharp angles more challenging than on plasterboard or tiles.
‱ Vinyl on both wall and floor: Always results in rounded internal corners. If you prefer a crisper line, tape the corners when applying the final coat, giving the appearance of straight rather than coved transitions.
‱ Tiles on wall and vinyl on floor: When you skim and level the height difference at the vinyl wall upstand, the transition straightens out and creates a clean edge automatically.

1. Leveling Height Differences & Floor Drains

Upstands & Transitions (Tiled wall / Vinyl floor)

Prime the vinyl upstand against the wall using an adhesion promoter for non-porous substrates (e.g. Ardex P4). Level the transition flush with the tiles using a polymer-modified cement compound or tile adhesive. Alternatively, fix a slim building board to align flush with the tile face.

Floor Drain & Gulley Grate

‱ New grate: To eliminate plastic grates resting on and wearing the surface, a microcement drain grate (e.g. Purus Sun) or mosaic drain insert is recommended. Bond the drain unit using hybrid adhesive and build up flush with tile adhesive prior to applying microcement.
‱ Existing clamp ring: If retaining the original clamping ring, bring primer, reinforcement mesh, and microcement neatly right down to the inner lip of the ring.

2. Priming Vinyl Flooring

Floor: Forprime DPM

2-component epoxy primer for non-porous vinyl floors.

‱ Application: Roll apply Forprime DPM evenly across the entire vinyl floor surface.
‱ Forprime HB/FL only requires a quartz sand broadcast if the base coat will not be applied within 24 hours.
‱ Curing: Allow to cure for a minimum of 6 hours before applying subsequent layers.
Wall: Monogrip

Textured adhesion primer with aggregate profile for vertical surfaces.

‱ Application: Roll apply a uniform, thin coat of Monogrip over the vinyl wall covering.
‱ Build-up: Standard primer when building up walls with Monostone XL and reinforcement mesh.
‱ Drying Time: Allow to dry for approx. 30–60 minutes prior to applying base coats.
⏳ Drying Times, Curing & Ventilation: Ensure leveling compounds are fully dry and primers are fully cured/dry before applying base coats. Maintain active air circulation throughout the space using open doors and ventilation fans.

3. Next Steps

Review primer options or proceed directly to bathroom application instructions:

How did we do?

FC - Application on Self-Levelling Screed/Concrete Floors (ENG)

FC - Application on Waterproofing Membranes (ENG)