FC - Application on Waterproofing Membranes (ENG)

How to prepare an approved waterproofing membrane in bathrooms for Forcrete: drain grate, tile adhesive skim, drying times and choice of primer.

tomas martinsson
Updated by tomas martinsson
Tradesperson Guide / Wetrooms

Application on Waterproofing Membranes

Instructions for drain grate installation, adhesive bed skimming, drying times, and primer selection over approved waterproofing membranes.

đŸ›Ąïž Approved Waterproofing Systems:
We recommend membrane systems from Kiilto or Zebra as they approve our products. Certified training for both systems is available by contacting us. Zebra provides complete tile installation manuals as well as quality assurance documentation to complete throughout the project.
🛑 Before commencing the project:
‱ Fully Dry Adhesive: Ensure the adhesive bed is completely dry through its entire depth before applying microcement. If trapped moisture remains, the adhesive risks shrinkage cracking, which will telegraph into and crack the microcement. Rapid-setting adhesive is strongly preferred.
‱ Water Ratios: Following precise water-to-powder ratios is essential to achieve structural strength and prevent curing shrinkage.
‱ Inspecting Cracks: Should any cracks appear in the adhesive bed prior to microcement application, they must be addressed first. Consult the membrane or adhesive manufacturer for proper remedial action.

1. Floor Drain Grate Installation

‱ Complete Bathroom in Forcrete: Bond the drain grate directly to the waterproofing membrane using an approved sealant/adhesive (we typically use Tec7, but always verify compatibility with the membrane manufacturer).
‱ Forcrete on Floor Only: Bond the drain grate over the gully, extend the adhesive bed flush to the perimeter walls, and fully complete the microcement build-up out to the membrane before wall tiles are installed. If this sequence is not possible, the grate must instead be bedded in tile adhesive so that any water tracking down the walls can migrate into the drain.

2. Application of Tile Adhesive / Render Bed

Walls — Leveling Membrane Overlaps

Adhesive on the walls creates a stable bonding bridge over the membrane and smooths out all sheet lap joints. Because microcement only builds approx. 2–4 mm, proud overlap seams will telegraph through the finished surface. Do not underestimate this step, as thorough preparation eliminates significant corrective work later.

Floors — Aligning to Grate Profile & Falls

On the floor, apply adhesive to match the rim profile of the chosen drain grate (e.g. 4 mm for mosaic frames, 6 mm for standard grates). Wall-adjacent linear drains frequently require a thicker build-up. We recommend increasing the screed gradient slightly within the wet zone during substrate screeding to avoid excessive build outside the shower area. For thicker adhesive depths, embed an alkaline-resistant fiberglass mesh into the bed to guard against shrinkage stress.

💡 Technique for maximum bond and planar consistency:
First, key a tight contact coat into the membrane using the flat edge of the trowel to guarantee 100% wetting out and prevent hollow voids. Comb through with a notched trowel (avoid combing directly over tape/lap joints). On floors, choose a notch size a couple of millimeters taller than the drain rim. Once firm, collapse the ridges with a tight skim coat; a second tight skim is often beneficial to achieve a dead-flat plane.

3. Primer Selection on Dry Adhesive

Floors (Forprime DPM)
‱ Consumption: 120–150 g/mÂČ prior to Microbase XT or Forprime HB.
‱ Sand Broadcast: Always broadcast quartz sand to saturation if the next layer is Microbase XT. Prior to Forprime HB, sand is only required if Forprime HB is not applied within 24 hours.
Walls (Monoprime / Forprime EPWB)
‱ Monoprime (60–80 g/mÂČ): Used prior to applying Monostone XL.
‱ Forprime EPWB (60–80 g/mÂČ): Used prior to applying Microbase XT on walls.
‱ Verify that the primer is completely tack-free and dry before troweling base coats.

4. Next Steps

Once the primer has dried, proceed with the bathroom base coats and subsequent installation stages:

📑 Handover to Client: Always issue care and maintenance guidelines to the client upon completion of the bathroom to ensure the surface is maintained correctly using recommended pH-neutral cleaners.