💡 About Monoprime:
Monoprime is a water-based, fast-drying 1-component primer. It is used on absorbent wall substrates such as plasterboard, render, and plastered surfaces to bind dust, regulate substrate suction, and ensure optimal adhesion prior to applying Monostone XL or L.
📱 Coverage & Drying Time:
• Material Consumption: Approx. 50–70 g/m².
• Drying Time: Approx. 30–60 minutes (until the surface is completely dry).
• Application Tool: Apply using a microfiber roller.
⚠️ Important Information Before Starting:
• Working Temperature: Material, substrate, and ambient air temperatures must remain between +10 °C and +25 °C.
• Mixing: Ready to use; shake the container thoroughly before pouring into the roller tray.
• Storage: Store frost-free. Shelf life is 12 months in unopened original packaging.
• Container Management: Reseal tightly immediately after decanting the required amount.

1. Substrate Preparation

1.
Substrate Inspection: The wall substrate must be sound, dry, and free from dust, grease, and contamination.
2.
Vacuuming: Vacuum the wall thoroughly to allow the primer to penetrate properly into the substrate.

2. Application

Rolling the Primer
• Application: Pour the primer into a paint tray and roll an even, fully covering coat across the entire wall surface.
• Avoid Pooling: Distribute the material uniformly without runs, sags, or heavy overlap lines.
• Drying Time: Allow to dry for approx. 30–60 minutes until completely dry and tack-free.

3. Next Steps

Select the guide for the next phase of your chosen system build-up:

🛑 Health & Safety Equipment:
• Wear nitrile protective gloves during roller application.
• Wear safety glasses to protect against splashes.
• Ensure adequate workspace ventilation and keep out of reach of children.
⏱️ Drying Times & Tool Maintenance:
• Drying Time Prior to Plastering: 30–60 minutes.
• Cleaning: Wash rollers, paint trays, and tools with clean water immediately after use.