TT - Substrate Preparation on Tiles (ENG)
How to make wall and floor tiles completely flat before Topciment: remove silicone, sand, prime and skim over the grout lines.
Updated
by tomas martinsson
Guide / Preparation
Substrate Preparation: Skimming Over Tiles & Pavers
Instructions for preparing and skim coating tiled walls and floor tiles prior to microcement application.
🛑 Before commencing the project:
• Substrate Preparation & Cleanliness: Ensure the surface is sound, dry, and thoroughly cleared of dirt and grease.
• Working Temperature: Ambient and substrate temperatures must be maintained between +10 °C and +25 °C throughout the entire preparation phase.
• Material Selection: These guidelines are based on Ardex A46 as the repair compound, though other cementitious, water-resistant repair mortars and polymer-modified tile adhesives may also be used.
• For larger floor areas with tiles, a thin coat of self-leveling screed is recommended instead.
• Substrate Preparation & Cleanliness: Ensure the surface is sound, dry, and thoroughly cleared of dirt and grease.
• Working Temperature: Ambient and substrate temperatures must be maintained between +10 °C and +25 °C throughout the entire preparation phase.
• Material Selection: These guidelines are based on Ardex A46 as the repair compound, though other cementitious, water-resistant repair mortars and polymer-modified tile adhesives may also be used.
• For larger floor areas with tiles, a thin coat of self-leveling screed is recommended instead.
1. Preparation and Grinding
2. Skimming and Leveling
💡 Critical for the Final Outcome:
Microcement only builds 2–3 mm in total and cannot conceal underlying substrate imperfections. If joint lines or ridges can be felt by hand, the grid pattern risks ghosting through under critical glancing light after sealing. The substrate must therefore be completely flat before moving to the next stage.
Microcement only builds 2–3 mm in total and cannot conceal underlying substrate imperfections. If joint lines or ridges can be felt by hand, the grid pattern risks ghosting through under critical glancing light after sealing. The substrate must therefore be completely flat before moving to the next stage.
3. Next Steps: Primers & Build-up
How did we do?