FC - Application on Tiles (Floor)
Craftsman Guide / Floor Systems Application: Tile Floors & Pavers. Practical guide for build-up, layer systems, and application of Forcrete microcement on tile floors and pavers.. 🛑 Before Starting t…
Updated
by tomas martinsson
Craftsman Guide / Floor Systems
Application: Tile Floors & Pavers
Practical guide for build-up, layer systems, and application of Forcrete microcement on tile floors and pavers.
🛑 Before Starting the Project — Pre-Start Checklist:
• Sample Board: Always create a physical sample of at least 60×60 cm in the correct color and texture for client approval.
• Substrate Inspection: Check moisture levels, cracks, and any substrate movement thoroughly.
• Underfloor Heating: Turn off underfloor heating completely at least 24 hours before commencing work.
• Always review any substrate defects with the client prior to starting.
• Sample Board: Always create a physical sample of at least 60×60 cm in the correct color and texture for client approval.
• Substrate Inspection: Check moisture levels, cracks, and any substrate movement thoroughly.
• Underfloor Heating: Turn off underfloor heating completely at least 24 hours before commencing work.
• Always review any substrate defects with the client prior to starting.
💡 Considerations for Tile Substrates:
• No Pre-filling on Normal Joints: Two coats of Forprime HB/FL will completely bridge and conceal standard grout lines.
• Large Joints or Uneven Surfaces: If tiles are uneven or grout lines are unusually deep and wide, a thin self-leveling screed is recommended before starting.
• Check for Hollow Tiles: Tap across the entire floor to detect hollow or loose tiles. Secure or remove all loose tiles.
• No Pre-filling on Normal Joints: Two coats of Forprime HB/FL will completely bridge and conceal standard grout lines.
• Large Joints or Uneven Surfaces: If tiles are uneven or grout lines are unusually deep and wide, a thin self-leveling screed is recommended before starting.
• Check for Hollow Tiles: Tap across the entire floor to detect hollow or loose tiles. Secure or remove all loose tiles.
1. Substrate Preparation & Setup
1.
Remove Soft Joints: Cut away all silicone and soft expansion joints in corners and transitions. Microcement does not adhere to silicone.
2.
Concrete Grinding: Grind tiles with diamond tooling to abrade the glaze and flatten lipped tile edges. Vacuum the surface completely clean of grinding dust.
2. Build-Up: Tile Floors & Pavers
Instructions: Reinforcement Guide ↗
Instructions: Apply Forprime HB/FL ↗
Instructions: Apply Microquartz ↗
Instructions: Mixing & Pigmentation ↗
3. Final Sanding & Sealing
Once the final coat of microcement has cured, sand the entire surface smooth with 50–200 grit depending on the selected finish. Vacuum and wipe down the floor with extreme care using a microfiber cloth prior to applying sealer.
4. Workflow & Day-by-Day Schedule
⚡ Time-Efficient Fast-Track (Save 1 Day):
If schedule is tight, the workflow can be shortened by a full day. Concrete-grind and roll Forprime DPM in the morning. As soon as the primer has dried, glue the mesh and trowel the first layer of Forprime HB/FL with full sand blinding that same afternoon.
If schedule is tight, the workflow can be shortened by a full day. Concrete-grind and roll Forprime DPM in the morning. As soon as the primer has dried, glue the mesh and trowel the first layer of Forprime HB/FL with full sand blinding that same afternoon.
⏳ Curing and Surface Loading:
• Foot Traffic: The floor can be walked on carefully in socks after 24 hours.
• Furniture: Do not place furniture on the floor for at least 5 days. Always use protective felt pads.
• Covering & Rugs: Do not cover the floor with rugs or protective paper for at least 14 days, as the topcoat requires time to fully cure and breathe.
• Water & Cleaning: Do not expose the surface to water or cleaning chemicals during the first 7 days.
• Foot Traffic: The floor can be walked on carefully in socks after 24 hours.
• Furniture: Do not place furniture on the floor for at least 5 days. Always use protective felt pads.
• Covering & Rugs: Do not cover the floor with rugs or protective paper for at least 14 days, as the topcoat requires time to fully cure and breathe.
• Water & Cleaning: Do not expose the surface to water or cleaning chemicals during the first 7 days.